The HVAC crew have moved on to refrigerant piping installation, while interior masons and CK’s steel crew began work on the pinch beam in the first-floor magistrate court. Exterior masons have re-installed the clock face frames and finished tuckpointing on the clock tower. The demo crew removed brick arches, and a wall on the second floor. Plumbing installation of the first and ground floors continues.