Electricians have continued roughing in walls on the ground, first, and second floors. Wood restoration and wood base priming remain ongoing. CK’s steel crew finished the Southwest roof steel install. The plaster crew has created plaster molds on the first floor and began installing plaster base on the ground floor. Interior masons continued elevator shaft erection. Roofers began roof tile and TPO roofing install on the clock tower roof. Demolition for the egress stair and elevator floor is now complete, and the plumbers have begun the ground floor in wall rough in.